'We know we made mistakes' on 737 MAX - Boeing CEO

  'We know we made mistakes' on 737 MAX - Boeing CEO 'We know we made mistakes' on 737 MAX - Boeing CEO"We have learned and are still learning from these accidents, Mr. Chairman. We know we made mistakes and got some things wrong," Muilenburg will tell the U.S. Senate Commerce Committee.

It has led to extensive delays getting the plane back into commercial service . The flight computer in the 737 Max was initially based on an older version Following the March 2019 crash of Ethiopian Airlines Flight 302, which was the second fatal crash involving a 737 Max in five months, Boeing engineers

Donald Trump grounded Boeing ’ s 737 Max fleet on Wednesday, days after the second fatal crash Boeing then decided to pull its entire fleet of 737 Maxes worldwide. What do we know about the The black box recorder has been recovered from the wreckage, which should reveal technical flight data

a group of cockpit: The cockpit of Boeing 737 Max 8 aircraft in June 2018. The cockpit of Boeing 737 Max 8 aircraft in June 2018.
  • A near-crash during a flight-simulator session in June led to a complete redesign of the Boeing 737 Max's flight computer architecture, according to a new Bloomberg report.
  • That redesign is in addition to the software fix to an automated system that caused two fatal crashes. It has led to extensive delays getting the plane back into commercial service.
  • The flight computer in the 737 Max was initially based on an older version of the 737, but is now considered antiquated. The redesign brings the computer up to modern standards, better able to manage various automated systems.
  • Visit Business Insider's homepage for more stories.

A near-crash in a simulated flight in June, using the software fix Boeing designed for the 737 Max, led to the extensive, ongoing delay that has kept the plane grounded through at least November, according to a new Bloomberg report.

Qantas, Southwest stepping up checks for cracks in 737 NG aircraft after issues found

  Qantas, Southwest stepping up checks for cracks in 737 NG aircraft after issues found Qantas, Southwest stepping up checks for cracks in 737 NG aircraft after issues foundRepairing the cracks requires grounding the airplane, with remedial work costing an estimated $275,000 per aircraft, according to aviation consultancy IBA.

Boeing ’ s new chairman gave embattled CEO Dennis Muilenburg a vote of confidence Tuesday and said the chief executive is giving up any David Calhoun said the Boeing board believes Muilenburg “ has done everything right” and is positioning the Chicago company to return the 737 Max to service

Regulators uncover a new issue with the troubled aircraft that could delay its return to service . The Federal Aviation Administration (FAA) said it had identified the "potential risk" during simulator tests, but did not reveal details. The longer the 737 Max remains grounded, the more the costs will mount up

Following the March 2019 crash of Ethiopian Airlines Flight 302, which was the second fatal crash involving a 737 Max in five months, Boeing engineers began designing a software fix to prevent an automated flight-control system from erroneously activating. The plane type was grounded worldwide within two days of the crash.

Initially, Boeing said it would be able to develop and implement the fix to the automated system known as MCAS, or the Manoeuvring Characteristics Augmentation System within a matter of weeks, later revising that to several months in order to fully test and certify the new software.

Qantas in Boeing 737 safety blitz

  Qantas in Boeing 737 safety blitz The airline is stepping up checks for structural cracks on its Boeing 737 NG fleet after discovering problems with a key component.The cracks are on what is known as the "pickle fork" - a part that attaches the plane's fuselage, or body, to the wing structure.

According to Boeing , the software helped the Max 8 handle like earlier 737 s . With a bigger engine Boeing has said it began working on its software fix immediately, but that the work proved more To test the new system and convince regulators, the company ran computer models subjecting the fix to

The US FAA has provided an update for when they expect that the Boeing 737 MAX may return to Not only did Boeing complete the development of the updated software for the 737 MAX , but they That’ s why it’ s interesting to note what the FAA is expecting. Reuters reports that the US FAA has

But in June, as engineers were almost finished designing the fix, several Boeing pilots got into a flight simulator to test "a few things." That was when a simulated computer glitch caused the plane to point its nose down, diving aggressively like the planes in both crashes.

The outcome of that simulator flight, a decision to completely redesign the 737 Max's flight computer architecture, led to extensive delays that have dragged on through the summer and fall, and now threaten Boeing's ability to deliver aircraft, book new orders, and maintain revenue expectations.

The extensive redesign, in addition to taking engineers longer, has also led to delays getting clearance from regulators, who are now looking more closely at the changes. Earlier this week, regulators demanded additional documentation from Boeing on the updates.

While the fix originally focused on MCAS, closer scrutiny of the entire plane following the second crash began to look at additional factors, including how pilots would respond to multiple cockpit alarms, and what would happen in both common and extremely remote emergency scenarios.

Qantas to finalise Boeing 737 checks over cracks

  Qantas to finalise Boeing 737 checks over cracks Qantas is expected to finalise an audit into 33 of its aircraft as engineers call for the airline to ground its Boeing 737 fleet.Nine Network Finance Editor Ross Greenwood told Today the airline's customers were receiving "mixed signals" about the safety of the aircraft.

The Boeing 737 MAX has been grounded for over two months now. Airlines will be very grateful to see the MAX return to service . This summer is anticipated to be one of the busiest Before the dual disasters of recent months, many air travelers would not have taken much notice of the equipment

Boeing is aiming for a return to service in the fourth quarter of this year, but American and United airlines have pulled Max flights Boeing revealed in July that it had taken a .6 billion pretax The use of new , bigger engines on the 737 Max required Boeing ’ s designers to mount the turbines farther

In the test that led to the computer redesign, Bloomberg reported, Boeing tested what would happen if gamma rays from space corrupted data in the plane's flight-control system - an extraordinarily unlikely scenario, but one which must be addressed to prove to safety regulators that the plane is capable of surviving virtually any possible failure.

In the test, the plane dived toward the ground, and one of the test pilots found it difficult to respond to the various alarms and system failures in time to control the plane.

While the 737 Max previously had two separate computers - one which operated flight systems, and one which stood by in case the first failed - the redesign has both computers set to monitor each other. The original setup was relatively antiquated, and was borrowed from older generations of the 737. The change is more in line with modern flight design.

a man standing on a rocky beach: American civil aviation and Boeing investigators search through the debris at the site of the Ethiopian Airlines crash in March 2019. American civil aviation and Boeing investigators search through the debris at the site of the Ethiopian Airlines crash in March 2019.

MCAS and the two crashes

Investigations into the two crashes suggest that MCAS erroneously engaged and forced the planes' noses to point down. Pilots were unable to regain control of the aircraft. The two crashes -Lion Air flight 610 and Ethiopian Airlines Flight 302 - killed a total of 346 people.

Before the software fix, MCAS could be activated by a single sensor reading - in both crashes, the sensors are thought to have failed, sending erroneous data to the flight computer and, without a redundant check in place, triggering the automated system.

MCAS was designed to compensate for the 737 Max having larger engines than previous 737 generations. The larger engines could cause the plane's nose to tip upward, leading to a stall - in that situation, MCAS could automatically point the nose down to negate the effect of the engine size.

Boeing is aiming to submit the proposed fix - and the computer redesign - to the FAA and get the plane certified to fly again by the end of 2019. US airlines have pulled the jet from their schedules until at least January.

The new seal for the Navy's next aircraft carrier contains a hint about big changes coming to naval aviation .
The US Navy's latest aircraft carrier, the John F. Kennedy, will be christened in December and should be commissioned next year. The service recently published the carrier's official seal that commemorates its namesake and hints at what the future of naval aviation will look like. Visit Business Insider's homepage for more stories. This month, the US Navy unveiled the official seal for the future aircraft carrier John F. Kennedy, which was officially launched on October 29 - three months ahead of schedule.

—   Share news in the SOC. Networks

Topical videos:

usr: 3
This is interesting!