Canada Court throws out Trans Mountain pipeline challenge from City of Vancouver and Squamish Nation

09:11  25 may  2018
09:11  25 may  2018 Source:   cbc.ca

Crude oil spill reported at Kinder Morgan facility north of Kamloops

  Crude oil spill reported at Kinder Morgan facility north of Kamloops

B.C.'s Supreme Court has dismissed legal challenges to Kinder Morgan's Trans Mountain expansion project from the City of Vancouver and the Squamish Nation . In a pair of rulings issued Thursday morning, Justice Christopher Grauer found the province of British Columbia acted reasonably in issuing.

B.C.'s Supreme Court has dismissed legal challenges to Kinder Morgan's Trans Mountain expansion project from the City of Vancouver and the Squamish Demonstrators hold a banner at the Kinder Morgan facility in Burnaby. A B.C. Supreme Court judge has thrown out a challenge by the City of

a yellow sign with black text: A row of demonstrators at the Kinder Morgan facility in Burnaby.© Rafferty Baker/CBC A row of demonstrators at the Kinder Morgan facility in Burnaby.

B.C.'s Supreme Court has dismissed legal challenges to Kinder Morgan's Trans Mountain expansion project from the City of Vancouver and the Squamish Nation.

In a pair of rulings issued Thursday morning, Justice Christopher Grauer found the province of British Columbia acted reasonably in issuing an environmental assessment certificate to the company.

As Grauer pointed out in his opening remarks to both cases, the decisions are not the end of the legal hurdles facing the pipeline. They dealt strictly with the question of whether the province could defend its actions in light of the National Energy Board's approval of the project.

After all the talk, deadline date for Trans Mountain nears without clear picture of the future

  After all the talk, deadline date for Trans Mountain nears without clear picture of the future Decision day is looming for the Trans Mountain pipeline expansion, but there's no clear sign of an outcome despite weeks of politics and closed-door talks. "This is really the make-or-break week for this particular project," said Warren Mabee, director of the Queen's Institute for Energy and Environmental Policy.

The City of Vancouver and Squamish Nation have lost court challenges over the Trans Mountain pipeline “The Supreme Court of British Columbia threw out two more challenges to the project. BREAKING: City of Vancouver ’s bid to have a judicial review of BC’s issuance of environmental

Court throws out Trans Mountain pipeline challenge from City of Vancouver and Squamish Nation . While analysts have said Kinder Morgan But even if government decided to buy into the pipeline business, the Trans Mountain expansion would still face the same challenges with protests

"This case is not about whether the TMX [Trans Mountain expansion project] should or should not go ahead. It is not about whether the TMX is in the national interest, or presents an unacceptable risk of environmental harm," Grauer wrote.

"This case is not about the adequacy of the consultation that was undertaken through the National Energy Board [NEB] and federal cabinet processes, nor does it resolve or define beyond currently settled law the constitutional limits on what either British Columbia or Alberta can or cannot do in relation to the project."

a sign in the middle of a park: Protesters and RCMP outside Kinder Morgan facility in Burnaby.© Darryl Dyck/Canadian Press Protesters and RCMP outside Kinder Morgan facility in Burnaby.

The Trans Mountain expansion would triple the amount of oil being transferred from Alberta to the Kinder Morgan terminal in Burnaby, B.C. The number of oil tankers in the water would also increase to 35 from five each month.

May gets $1,500 fine for contempt of court

  May gets $1,500 fine for contempt of court VANCOUVER - Green party Leader Elizabeth May has pleaded guilty to a criminal contempt of court charge for violating an injunction at a Kinder Morgan work site in Burnaby, B.C. May was arrested in March at a Trans Mountain pipeline terminal in Burnaby when she joined activists including New Democrat MP Kennedy Stewart, who pleaded guilty to the same charge earlier this month. B.C. Supreme Court Justice Kenneth Affleck had imposed an injunction requiring protesters to stay at least five metres away from two work sites in Burnaby.

B.C. Supreme Court threw out challenges against the Kinder Morgan pipeline from the City of Vancouver and the Squamish Nation . This is good news for the rest of Canada to help give the economy somewhat of a boost if Kinder Morgan doesn’t go past its deadline next week. Via CBC.

The Trans Mountain Pipeline System, or simply the Trans Mountain Pipeline , is a Despite federal government approval, seven Federal Court challenges were filed by the municipalities of Vancouver and Burnaby, and the Tsleil-Waututh, Squamish , Kwantlen, and Coldwater First Nations .[22] In

The City of Vancouver claimed that in reviewing the Trans Mountain project, the province failed to engage in proper consultation and failed to conduct a proper environmental assessment.

a close up of a sign: The City of Vancouver claimed the province failed to engage in proper consultation or environmental assessment. The Squamish Nation argued that the province should have done a further assessment to make up for a flawed NEB process.© Erin Collins/CBC The City of Vancouver claimed the province failed to engage in proper consultation or environmental assessment. The Squamish Nation argued that the province should have done a further assessment to make up for a flawed NEB process.

For its part, the Squamish Nation argued the province should have done a further assessment to make up for what it maintained was a "fundamental failure of the process of consultation and accommodation" by the NEB.

Limitations of the ruling

In regard to the Vancouver case, Grauer went to great pains to clarify what questions his court could and could not answer. He said the current provincial government's challenge to the federal government's authority was not part of the litigation before him, nor was the decision of the federal cabinet to approve the project.

Federal government expected to announce financial plan for Trans Mountain pipeline Tuesday morning

  Federal government expected to announce financial plan for Trans Mountain pipeline Tuesday morning Federal government expected to announce financial plan for Trans Mountain pipeline Tuesday morning There are three options on the table, which include the government buying and building the expansion, then selling it once it's complete; and buying it on an interim basis, then selling it to investors and leaving them to handle the construction.

B.C.'s Supreme Court has dismissed legal challenges to Kinder Morgan's Trans Mountain expansion project from the City of Vancouver and the Squamish …

Court throws out Trans Mountain pipeline challenge from City of Vancouver and Squamish Nation . More. First Nations and municipal leaders restated their opposition to the Kinder Morgan Trans Mountain pipeline expansion project in no uncertain terms Monday in Vancouver .

"Did [the province] follow the law? Did it act with procedural fairness? Did it act reasonably and in compliance with its own statutory processes?" Grauer asked.

"These are the questions that the courts are equipped to answer, subject always to the considerable constraints imposed by the standards of review that the courts are obliged to employ."

As far as the concerns of the Squamish Nation are concerned, Grauer noted that the Federal Appeal Court is currently considering the adequacy of the NEB's Aboriginal consultation.

But the judge concluded that "adequate consultation did not require British Columbia to correct any perceived shortfall in the NEB process."

He said the province "considered the options constitutionally open to it, and proceeded accordingly."

"There is no doubt that Squamish is deeply disappointed in the approval of the TMX notwithstanding the conditions attached to that approval. It strenuously opposed the project and continues to do so," Grauer wrote.

"But ... I must concern myself not with the result but with the process."

Trans Mountain pipeline project purchase ‘major step forward’: Rachel Notley

  Trans Mountain pipeline project purchase ‘major step forward’: Rachel Notley Trans Mountain pipeline project purchase ‘major step forward’: Rachel NotleyAlberta's premier calls the decision by the federal government to purchase the Trans Mountain Pipeline expansion project for $4.5 billion "a major step forward for all Canadians.

The City of Vancouver and Squamish Nation aren’t giving up their legal fight against the Trans Mountain pipeline expansion . The city and the Nation have filed notice of appeal to the B.C. Court of Appeal, after losing a pair of separate court challenges .

B.C.'s Supreme Court has dismissed legal challenges to Kinder Morgan's Trans Mountain expansion project from the City of Vancouver and the Squamish Nation .

On Thursday, the City of Burnaby also filed another action with the Federal Court of Appeal, asking for a judicial review of the energy's board's approval of the pipeline route. It argued the construction would do serious damage to many areas of the city.

Squamish Nation reacts

A posting on Facebook says the Squamish First Nation had just received the decision and was disappointed. But spokesperson Khelsilem pointed out that the decision was only about provincial approval and that the First Nation is also part of the challenge in the Federal Court of Appeal.

"We have a right to practice our culture, our way of life, and to continue our right to self-determination in our territories," Khelsilem wrote. "This is a right that we have never surrendered, and it is a right we will continue to defend."

The City of Vancouver also released a statement saying it was "disappointed" with the decision.

B.C. Attorney General David Eby said both cases involved decisions made by the previous Liberal government, but the NDP government still argued that the provincial Crown had fulfilled its legal duty to consult the Squamish Nation.

"Our government has taken a balanced approach to defending our environment and our economy while fulfilling our legal obligations and respecting the rule of law," Eby said.

The province took no position on the merits of the Vancouver claim.

Kinder Morgan said it was pleased with the court's decision.

Meanwhile, Alberta Premier Rachel Notley said she was happy to see at least one legal hurdle fall.

"This pipeline is unlike any other in that it has been rigorously reviewed, meaningful consultation has taken place and it is paired with an effective climate protection plan," she said in a statement.

"The failures of the past will not be repeated. The government of Alberta will not stop fighting until we get the job done. We will get this pipeline built."

Both parties have 30 days to appeal. Vancouver said it is considering its options.

Grauer has also ordered the City of Vancouver to pay Trans Mountain's legal costs for fighting the city's petition.

Activist expects unprecedented pipeline protests .
VANCOUVER - Outrage over the federal government's announcement about buying the Trans Mountain pipeline to ensure it gets built could fuel unprecedented protests, says a prominent environmentalist who was at the forefront of British Columbia's so-called War in the Woods in the 1990s. Tzeporah Berman said the fight against the pipeline expansion is even bigger than those over logging in Clayoquot Sound. Canadians are angry the government is shelling out $4.

—   Share news in the SOC. Networks

Topical videos:

This is interesting!