Technology Trans Mountain received $320M in government subsidies in first half 2019: report

12:07  20 november  2019
12:07  20 november  2019 Source:   msn.com

Emergency response at Trans Mountain’s Burnaby tank farm could take 6 hours: Report

  Emergency response at Trans Mountain’s Burnaby tank farm could take 6 hours: Report The 2016 was not made public, and only came to light through a freedom of information request by Burnaby election candidate Svend Robinson.The report estimates Trans Mountain's planned response time to a major event, such as a serious fire, at six hours.

The Trans Mountain pipeline received $ 320 million in subsidies from the Canadian and Alberta governments in the first half of 2019 , says a new report by an economic institute that analyzes environmental issues. The money included 5.8 million in direct subsidies and 3.8 million in

VANCOUVER - The Trans Mountain pipeline received $ 320 million in subsidies from the Canadian and Alberta governments in the first half of 2019 , says a new report by an economic institute that analyzes environmental issues. The money included 5.8 million in direct subsidies and

  Trans Mountain received $320M in government subsidies in first half 2019: report © Provided by Canadian Press Enterprises Inc

VANCOUVER — The Trans Mountain pipeline received $320 million in subsidies from the Canadian and Alberta governments in the first half of 2019, says a new report by an economic institute that analyzes environmental issues.

The money included $135.8 million in direct subsidies and $183.8 million in indirect subsidies that were not clearly disclosed to taxpayers, says the report by the Institute for Energy Economics and Financial Analysis.

"This is a very large subsidy. It really does require more public discussion and public disclosure," says Tom Sanzillo, the group's director of finance and a former deputy comptroller of the state of New York.

Trans Mountain adds thousands of new positions for pipeline expansion project

  Trans Mountain adds thousands of new positions for pipeline expansion project Prime Minister Justin Trudeau has promised the project will go ahead.In a news release, the company says 2,200 new positions have been added since Sept. 30 for the expansion project, with a focus on Indigenous, regional and local workers.

VANCOUVER—The Trans Mountain pipeline received $ 320 million in subsidies from the Canadian and Alberta governments in the first half of 2019 , says a new report by an economic institute that Finally, the Alberta government reduced corporate taxes through a tax credit starting in January 2019 .

The Trans Mountain pipeline received $ 320 million in subsidies from the Canadian and Alberta governments in the first half of 2019 , says a new report by an economic institute that analyzes environmental issues. The money included 5.8 million in direct subsidies and 3.8 million in

Sanzillo and the report's co-author, institute financial analyst Kathy Hipple, analyzed the second-quarter report of the Canada Development Investment Corp., a Crown corporation meant to further the country's economic development that counts Trans Mountain Corp. among its subsidiaries.

The document is public but presents a consolidated picture of the development corporation's finances, including revenues from the Canada Hibernia Holding Corp., which operates the Crown's interest in oil reserves off Newfoundland and Labrador.

This accounting treatment obscures the real financial state of Trans Mountain, Sanzillo says.

"It's a good form of accounting. I'm not criticizing it. It just shouldn't be the only mechanism for showing the public how much money is being spent on this," he says.

Trans Mountain received $320M in government subsidies in first half 2019: report

  Trans Mountain received $320M in government subsidies in first half 2019: report VANCOUVER — The Trans Mountain pipeline received $320 million in subsidies from the Canadian and Alberta governments in the first half of 2019, says a new report by an economic institute that analyzes environmental issues. The money included $135.8 million in direct subsidies and $183.8 million in indirect subsidies that were not clearly disclosed to taxpayers, says the report by the Institute for Energy Economics and Financial Analysis. "ThisThe money included $135.8 million in direct subsidies and $183.8 million in indirect subsidies that were not clearly disclosed to taxpayers, says the report by the Institute for Energy Economics and Financial Analysis.

VANCOUVER – The Trans Mountain pipeline received $ 320 million in subsidies from the Canadian and Alberta governments in the first half of 2019 , says a new report by an economic institute that analyzes environmental issues. The money included 5.8 million in direct subsidies and

The Trans Mountain pipeline received $ 320 -million in subsidies from the Canadian and Alberta governments in the first half of 2019 , says a new report Mr. Sanzillo also identifies what he calls an indirect subsidy ; the difference between the interest a private company would have charged Trans

The Canadian government gave the development corporation just over $5 billion to finance the acquisition of Trans Mountain, the report says. Trans Mountain Corp. must make regular interest payments to the Canadian government at a rate of 4.7 per cent.

The cash was provided to Trans Mountain in two sections: a $2.8 billion loan and a $2.3 billion equity investment. The interest on the loan must be paid from the pipeline's business activity, while the interest on the equity investment can be paid from a third-party subsidy, the report says.

Energy exodus: oil and gas workers look for more opportunity in Texas

  Energy exodus: oil and gas workers look for more opportunity in Texas The oil and gas sector is struggling to get its 'Alberta Advantage' back and that has many looking elsewhere for opportunity. Some are finding it, in Texas.But ever since the last bust — when world oil prices collapsed in 2014 and tens of thousands of energy workers lost their jobs — Alberta has struggled to regain its footing.

VANCOUVER — The Trans Mountain pipeline received $ 320 million in subsidies from the Canadian and Alberta governments in the first half of 2019 , says a new report by an economic institute that analyzes environmental issues. The money included 5.8 million in direct subsidies and

Trans Mountain received $ 320 M in government subsidies in 2019 , report finds. Many of the documents are "activity reports " compiled by Trans Mountain . The activity reports provided to CBC News appear to cover a period between Dec.

The Canada Hibernia Holding Corp. covered the interest on the equity investment for the first half of 2019, representing a direct subsidy of $46.3 million, the report says.

Trans Mountain posted a $10.9 million loss in this reporting period prior to taxes, the report says.

However, the loss is subsidized in the consolidated financial report by the Hibernia corporation's earnings, amounting to another $10.9-million direct subsidy, the report says.

No less controversial, Trans Mountain continues on with expansion project

  No less controversial, Trans Mountain continues on with expansion project Construction crews remain busy driving piles for new facilities at Trans Mountain’s Westridge marine terminal on Burrard Inlet and clearing land at the Burnaby Mountain terminus of its pipeline, but industry leaders remain apprehensive about the expansion project. “Everyone is guarded about what does this mean,” said Chris Gardner, president of the Independent Contractors and Business Association about last week’s announcement that construction on the $7.4 billion project had officially restarted.

READ MORE: $ 320 M in government subsidies given to Trans Mountain in first half of 2019 : report . Federal Election 2019 : What could a Liberal minority mean for the Trans Mountain Pipeline. The existing Trans Mountain pipeline carries about 300,000 barrels a day of crude oil and related

The report , Trans Mountain Pipeline Financials Suggest Taxpayer Dollars at Risk, also shows that substantially more subsidies will be required to complete the project, while the amount of subsidies is not clearly identified in Canadian government financial disclosures.

Sanzillo also says the development corporation uses an "accounting gimmick" to obscure Trans Mountain's pension liability of $24.4 million. This is one more direct subsidy, he says.

Finally, the Alberta government reduced corporate taxes through a tax credit starting in January 2019. This policy action allowed Trans Mountain to save $54.1 million in taxes, yet another direct subsidy that the development corporation uses to turn the corporation's pre-tax loss into a post-tax gain, according to the report.

A representative for Trans Mountain referred all questions about the report to the Department of Finance, which says that the government does not consider any part of its investment in the pipeline to be a subsidy.

The department says in a statement late Tuesday that Trans Mountain Corp. is undertaking a major expansion and incurring associated expenses without any related revenues, which is "normal" during the development phase of any big project.

It also says the government extended loans using commercial-level rates and it still considers the expansion project to be economically viable.

First Nations in court this week arguing Trans Mountain pipeline expansion should be quashed — again

  First Nations in court this week arguing Trans Mountain pipeline expansion should be quashed — again Several B.C. First Nations will be squaring off against the federal government in the Federal Court of Appeal in Vancouver this week, arguing that it failed to conduct meaningful consultations with them about the Trans Mountain pipeline expansion and that the project should be cancelled. The case is similar to the previous Federal Court of Appeal case that quashed the approval of the pipeline expansion in August 2018 except it is focused on the specific window of time when the federal government revisited its duty to consult with First Nations before approving the project once again in June of this year.

"The government expects to realize a positive financial return on its investment," the statement says.

Sanzillo, however, identifies what he calls an indirect subsidy — the difference between the interest a private company would have charged Trans Mountain versus the rate charged by the Canadian government.

Canada's 4.7 per cent interest rate stands in contrast with the 12 to 15 per cent rate of return used by its former owner, Kinder Morgan, the report says.

Sanzillo used the lower figure, 12 per cent, to calculate that a private company would have charged Trans Mountain $302.1 million in interest in the first half of 2019. The Canadian government, meanwhile, charged it $118.3 million.

That amounts to an indirect subsidy of $183.8 million for the first six months of the year, according to the report.

The report authors acknowledge that the Canadian government does not have to adhere to commercial standards.

"(The report) is about transparency and not meant to be a legal challenge to the right of the Canadian government to subsidize the pipeline project. It is a matter of dollars at risk that the Canadian taxpayer might absorb," it says.

When the authors added the $46.3-million interest payment and the $24.4-million pension expense back to Trans Mountain's financials, they concluded the pipeline corporation had a $67.1-million pre-tax loss and a $12.9 million loss after taxes.

The Canadian government plans to ultimately sell the pipeline. If it does so for a lower price than it paid for the infrastructure, it can legally forgive any debt that is left over, Sanzillo adds.

This report by The Canadian Press was first published Nov. 19, 2019.

Laura Kane, The Canadian Press

Top court's TMX decision a 'slap-down' for B.C., Alberta government says .
The Supreme Court of Canada has delivered its verdict on B.C.'s attempt to challenge the Trans Mountain expansion project — and its decision was music to the Government of Alberta's ears.The British Columbia government's appeal represented one of many legal hurdles for the delayed and embattled expansion project, and its dismissal quickly drew a positive statement from Alberta Premier Jason Kenney.

—   Share news in the SOC. Networks
usr: 0
This is interesting!